Project: Reconstruction and extension of office block (sanitary and garage – warehouse premises) in Siedlce, Spokojna Street
Investor: Power Station „Warszawa – Teren”
Location: Siedlce Spokojna Street
Duration time of project: 18 months
Project value: 4.23 mln PLN
Our participation: all construction works
Project: Willa Magdalenka
Investor:
Location: Magdalenka
Duration time of project:
Project value:
Our participation:
Project: Dwelling house – Willa Pärnilla
Investor: data restricted
Location: Västra Tye near Karlstad
Duration time of project: 15 months
Project value: data restricted on Investor’s request
Our participation: General Contractor (except foundation and installation works)
Project: Restaurant in Skoghall
Investor: Erwin Restaurang och Pizzeria
Location: Skoghall
Duration time of project: 2 months
Project value: 110 000 PLN
Our participation: Designing and completing renovation and modernization works
Project: Construction works on „A” and „B” segment of building „H” – Power Station “Warszawa – Teren”
Investor: Power Station „Warszawa – Teren”
Location: Marsa 95, Warsaw
Duration time of project: 12 months
Project value: 1.42 mln PLN
Our participation: roof renovation and termo – renovation; finishing works
Project: Industrial Laundry
Investor: Zakrisdals Företagscentrum
Location: Zakrisdalsvägen 22, 653 42 Karlstad
Duration time of project: 1 month
Project value: 70 000 PLN
Our participation: All construction and finishing works
Project: Adaptating school for flats
Investor: Borensberg Fastighets AB
Location: Borensberg
Duration time of project: 4 months
Project value: data restricted on Investor’s request
Our participation: adaptation and finishing works
Project: Hildurs Modecompani – restoring cloth shop appearance from 30. of XX century
Investor: Anna Lena Rudberg
Location: Tingvallaget 17, 65 224 Karlstad
Duration time of project: 0,25 month
Project value: data restricted on Investor’s request
Our participation: all renovation works
Project: Dwelling house renovation and modernization
Investor: Sune Carlsson
Location: Östra Rosenlundsgatan 10, 65461 Karlstad
Duration time of project: 6 months
Project value: Data restricted on Investor’s request
Our participation: all renovation and modernization works

Anna Lena Rudberg

Precision and teamwork
Flexor has done all the renovations in my boutique. The ceiling and the inner wall were torn down and the former built-in stairs have now been made visible. Flexor's workers are very thorough and we had an incredible teamwork. It is very important for me that everything turns out the way I want and I have also hired Flexor for some renovations in my private home.